Stakeholder Engagement
One thing consistent with all healthcare projects is the huge number of stakeholders, often with opposing priorities and needs. As care is devolved further into communities, with new facilities to serve that purpose, managing the needs and expectations of a diverse range of stakeholders will get more complex.
As main contractor, we lead with engagement of stakeholders at the critical design stage as it will have a huge impact on outcomes. For the Tessa Jowell Centre in Dulwich, this involved workshops with 23 stakeholder groups at project inception to tease out what people expected from their new facility.
“We wanted to get as close to the customer as we could,” says Willmott Dixon construction manager Steve Harnett. “The workshops helped us to understand the ‘why’ of the customer, an essential building block at the start.”
During construction, communication was maintained with progression workshops, formal progress reports and informal, weekly bullet-point summaries which went out to up to 28 stakeholders, while visits to site informed stakeholders on decisions about layout and quality.

Being tech-savvy
“We completed two rooms eight months before the end of the job, complete with furniture and lighting, so that we could tease out any problems or improvements,” says Harnett. Using augmented reality software inside room spaces to superimpose finishings and furnishings also helped communicate the finished space with visitors to site, adds Harnett.
A community asset that's fine legacy for Tessa
Sam Hepplewhite, Director for Southwark at NHS South East London CCG said:
“The new health centre will play an important role in helping to join together local services and help us to improve the health and wellbeing of people in south Southwark”